Keputusan Menteri Energi dan Sumber Daya Mineral Republik Indonesia No. 91 K/12/MEM/2020 tentang Harga Gas Bumi di Pembangkit Tenaga Listrik (Plant Gate) 

Ministry of Energy and Natural Resources Decree no. 91 K/12/MEM/2020 on Power Plant (Plant Gate) Gas Price

Pada 22 April 2020, Menteri Energi dan Sumber daya Mineral (“ESDM“) Indonesia menerbitkan Keputusan Menteri Energi dan Sumber Daya Mineral Republik Indonesia No. 91 K/12/MEM/2020 tentang Harga Gas Bumi di Pembangkit Tenaga Listrik (Plant Gate).

yang secara prinsipal berisi:

On 22 April 2020, the Indonesian Minister of Energy and Mineral Resources (“ESDM”) of issued Decree of the Minister of Energy and Mineral Resources of the Republic of Indonesia No. 91 K / 12 / MEM / 2020 concerning the Natural Gas Price in the Power Plant (Plant Gate) Indonesia.

which principally contains:

  • Menetapkan Harga Gas Bumi di Pembangkit Tenaga Listrik (Plant Gate) yang tercantum dalam Lampiran yang merupakan bagian tidak terpisahkan dari Keputusan Menteri ini.
  • Harga Gas Bumi di Pembangkit Tenaga Listrik (Plant Gate) sebagaimana dimaksud dalam Diktum KESATU merupakan perhitungan penyesuaian terhadap komponen harga Gas Bumi dari Kegiatan Usaha Hulu Minyak dan Gas Bumi serta biaya penyaluran yang terdiri atas biaya transportasi dan biaya midstream Gas Bumi.
  • Harga Gas Bumi di Pembangkit Tenaga Listrik (Plant Gate) sebagaimana dimaksud dalam Diktum KESATU dituangkan dalam
    • peijanjian jual beli Gas Bumi untuk pembangkit tenaga listrik antara penyedia Gas Bumi dengan PT PLN (Persero) dan/atau Badan Usaha Pembangkitan Tenaga Listrik; dan/atau
    • peijanjian penyaluran Gas Bumi antara Badan Usaha Pemegang Izin Usaha Niaga Gas Bumi dengan PT PLN (Persero) dan/atau Badan Usaha Pembangkitan Tenaga Listrik.
  • Satuan Kerja Khusus Pelaksana Kegiatan Usaha Hulu Minyak dan Gas Bumi atau Badan Pengelola Migas Aceh sesuai kewenangannya mengoordinasikan penyesuaian harga Gas Bumi dari Kegiatan Usaha Hulu Minyak dan Gas Bumi sebagaimana dimaksud dalam Diktum KEDUA kepada Kontraktor Kontrak Kerja Sama.
  • Penyelesaian Perjanjian Jual Beli Gas Bumi dan/atau dokumen administrasi lainnya terkait penyesuaian harga Gas Bumi dari Kegiatan Usaha Hulu Minyak dan Gas Bumi sebagaimana dimaksud dalam Diktum KEDUA, wajib diselesaikan paling lambat 1 (satu) bulan sejak Keputusan Menteri ini berlaku.
  • Badan Pengatur Hilir Minyak dan Gas Bumi mengoordinasikan dan menetapkan penyesuaian besaran biaya transportasi berupa tarif pengangkutan Gas Bumi melalui pipa dalam rangka penetapan Harga Gas Bumi di Pembangkit Tenaga Listrik [Plant Gate) sebagaimana dimaksud dalam Diktum KESATU.
  • Penyelesaian Surat Keputusan, Perjanjian Pengangkutan Gas Bumi, dan/atau dokumen administrasi lainnya terkait tarif pengangkutan Gas Bumi melalui pipa wajib diselesaikan paling lambat 1 (satu) bulan sejak Keputusan Menteri ini berlaku.
  • Menteri melalui Direktur Jenderal Minyak dan Gas Bumi melakukan evaluasi dan dapat melakukan peninjauan ulang terhadap penetapan Harga Gas Bumi di Pembangkit Tenaga Listrik (Plant Gate) sebagaimana dimaksud dalam Diktum KESATU.
  • PT PLN (Persero) dan/atau Badan Usaha Pembangkitan Tenaga Listrik menyampaikan laporan penggunaan volume dan Harga Gas Bumi di Pembangkit Tenaga Listrik (Plant Gate) sebagaimana dimaksud dalam Diktum KESATU, secara berkala setiap 6 (enam) bulan kepada Menteri melalui Direktur Jenderal Minyak dan Gas Bumi dengan tembusan Direktur Jenderal Ketenagalistrikan.
  • Determine the Natural Gas Price in the Power Plant (Plant Gate) listed in the Appendix which is an integral part of this Ministerial Decree.
  • Natural Gas Price in the Power Plant (Plant Gate) as referred to in the FIRST point is the calculation of adjustments to the component price of Natural Gas from Upstream Oil and Gas Business Activities and distribution costs consisting of transportation costs and midstream Gas costs.
  • Natural Gas Price in the Power Plant (Plant Gate) as referred to in the FIRST point is outlined in
    • agreement on the sale and purchase of Natural Gas for power plants between Natural Gas providers and PT PLN (Persero) and / or Electricity Generation Business Entity; and / or
    • agreement on the distribution of Natural Gas between a Business Entity Holder of a Natural Gas Commercial Business License with PT PLN (Persero) and / or an Electric Power Generation Business Entity.

 

 

  • The Special Task Force for Upstream Oil and Gas Business Activities or the Aceh Oil and Gas Management Agency in accordance with its authority coordinates the adjustment of Natural Gas prices from Upstream Oil and Gas Business Activities as referred to in the SECOND point to the Cooperation Contract Contractor (PSC Contractor).
  • Completion of the Natural Gas Sales and Purchase Agreement and / or other administrative documents related to the adjustment of the price of Natural Gas from the Upstream Oil and Gas Business Activities as referred to in the SECOND point, shall be completed no later than 1 (one) month after this Ministerial Decree comes into force.
  • The Downstream Oil and Gas Regulatory Agency coordinates and determines the adjustment of the amount of transportation costs in the form of tariffs for transporting natural gas through pipes in the context of setting the price of natural gas at the [Plant Gate] as referred to in the FIRST Point.
  • Settlement of Decisions, Natural Gas Transport Agreements, and / or other administrative documents related to the tariff for transportation of natural gas through pipelines must be completed no later than 1 (one) month after this Ministerial Decree takes effect.
  • The Minister through the Director General of Oil and Gas conducts an evaluation and can conduct a review of the determination of the Price of Natural Gas in the Power Plant (Plant Gate) as referred to in the FIRST point.
  • PT PLN (Persero) and / or Electricity Generation Business Entity reports on the use of the volume and Natural Gas Price in the Power Plant (Plant Gate) as referred to in the FIRST point , periodically every 6 (six) months to the Minister through the Director General of Oil and Natural Gas with a copy to the Director General of Electricity.
The documents can be downloaded at below link / dokumen dapat diunduh di tautan di bawah ini:

Keputusan Menteri ESDM no 91/K/12/MEM/2020

Frequently Asked Questions

[Question]
[Question]
[Answer]
[QUESTION]
[Answer]
[QUESTION]
[Answer]
[QUESTION]
[Answer]
error: Content is protected !!
Subscribe To Our Newsletter (Legal Alert and News)

Subscribe To Our Newsletter (Legal Alert and News)

Join our mailing list to receive the latest news and updates from our team.

You have Successfully Subscribed!